Construction Bulletin

City Projects - Capital Projects Engineering

Cobblestone Dr Zone R2-R4 Water Main Connection
The project will install approximately 1,045 linear feet of new 10-inch diameter water main and a pressure-reducing assembly that will connect a high-pressure zone with a lower-pressure zone to improve fire protection in the Cobblestone neighborhood. Approximately 174 linear feet of 8-inch diameter water main will be added near the southern end of Cobblestone Drive to provide operational flexibility including the ability to isolate the Cobblestone neighborhood into a separate pressure zone.  Project Details
(Team Ghilotti, Inc - Joe Moreira / City - Andrew Wilt)

Cleveland Ave & St. Rose District Sewer & Water Improvements
This project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs. Project Details
(W.R. Forde Associates - Tony Perez / City - Oscar Serrano)

Crosstown Trunk Lining - 3 Segments
This project aims to extend the useful life of a portion of the cross-town trunk sewer. CCTV observations have identified corrosion at the crown of the pipe. The project will examine various options for structural rehabilitation and then engage a contractor to perform the rehab work. Rehabilitation work will be performed at three locations along the trunk. Project Details
(Insituform Technologies - Adrian Padilla / City - Chris Huffman)

Curb Ramp Replacements - 2021
Remove existing barrier locations prioritized from our Top 100 Curb Ramp Needs list. Project Details
(City Crews, Daniel Schwartz Inc - 707- 526-3837 / City – Randy Lopez)

Emergency Well Pump Station – A Place to Play 
The purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and appurtenances associated with the Emergency Groundwater Well at A Place to Play Park. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water’s Groundwater website located at: https://srcity.org/857/Groundwater. Project Details
(Team Ghilotti - Joe Moreira / City - Chris Huffman)

Fire Damaged Roadway Landscaping
This project relates to the repair of the irrigation systems along the city owned and maintained roadway landscaping areas such as in planter strips and medians as the result from 2017 Tubbs Fire. The project limits are spread out across Fountaingrove and Coffey Park neighborhoods. The scope of the work includes the removal of the existing fire damaged irrigation systems, removal of approximately 300 trees in conflict with the proposed improvements, install new irrigation systems per city code. Project Details
(Bortolussi & Watkin, Inc-Juan Maravilla (415)453-4675 / Green Valley Consultants- Jason Balatti (707) 579-0388 / City - Danny Chen)

Fulton Road From Guerneville Road to Piner Road – Widen to Four Lanes
The Project will widen and reconstruct Fulton Road into four vehicle travel lanes with a median using roller compacted concrete (RCC), between Guerneville and Piner Road. The project widening will improve the City’s transportation network and promote multi-modal transportation with the installation of bike lanes and sidewalk widening along this one-mile corridor. This project has been envisioned in the Santa Rosa 2035 General Plan as an arterial/regional road to be widened to improve circulation, safety, and operation along Fulton Road. The Project is expected to begin construction in June 2022 and will take eighteen months to complete. Residents should expect traffic delays and watch for changing traffic conditions during construction. Project Details
(Ghilotti Bros / Vanguard Construction JV  - Casey Wood / Green Valley Consultants - Tom Gorman / City - Chad Anderson)

Geysers - Delta Connection Improvements
This project will upsize approximately 130 linear feet of the existing 12" diameter connection between the Geysers Pipeline and Delta Pond to 24" diameter. This will allow high flows of recycled water to be delivered to Delta Pond using the Geysers pipeline as a redundant supply line to the reclamation piping network. Project Details
(Piazza Construction - James Piazza / Consultant – Brelje and Race - Dana Brock / City – Michael Mirich)

Laguna Treatment Plant Disinfection Improvements Project
Ultraviolet light (UV) is the primary disinfection process for the City of Santa Rosa's Laguna Treatment Plant (LTP). The existing system was commissioned in 1998, has reached the end of its useful life, and no longer has the treatment capacity for peak wet weather sewer flows. Project Details
(Shimmick Construction - Jason Burden / Psomas - Chris Davenport)

Laguna Treatment Plant Emergency Generator Fuel Tank and Fleet Fueling Station Replacement
The outer wall of the existing emergency generator diesel fuel storage tank at the Laguna Treatment Plant has started to deform preventing monitoring of the annual space thus is out of compliance from a regulatory standpoint. The fuel storage tank is critical to insuring operation of the plant in the event of a power outage. The new tank will be an above ground storage tank. The project will replace the plant's existing diesel fueling station with a dual diesel/gasoline fueling station. Project Details
(CIC - Tuan Pham / City - Richela Maeda)

Laguna Treatment Plant Waste Gas Burner Replacement
This project will replace the Laguna Treatment Plant’s existing waste gas burner, which combusts any excess digester gas from the plant’s cogeneration system. The waste gas burner is nearing the end of its useful life and requires replacement to provide the plant with a safe and compliant system. 
Project Details
(Pacific Intrastructure - Mark Jorgenson / City - Richela Maeda)

Public Safety Building Hydronic Pipeline Replacement 
This project will replace the Public Safety Building (955 & 965 Sonoma Ave) hot and cold water supply and return lines for the building's hydronic boiler system. Project Details
(Peterson Mechanical, Inc. - Wayne Ritz / Green Valley Consultants – Jason Balatti / City – Chris Balanesi)

Santa Rosa Avenue Corridor Improvements
This project will make improvements to existing pedestrian, bike, transit, and vehicle facilities along Santa Rosa Avenue between Sonoma Avenue and Maple Avenue. The project will upgrade pedestrian facilities throughout the corridor, including upgrading pedestrian ramps to current ADA standards, and close gaps in the Class II bike lane network on Santa Rosa Avenue, while considering connectivity to Sonoma Avenue. Project Details
(Granite Construction – Cody Bedell / City – Randy Lopez)

Santa Rosa Pavement Rehabilitation of Various Streets
This project will rehabilitate various streets including asphalt resurfacing, restriping, addition of bike lanes, and curb ramp improvements. The coverage of the project includes the following limits: Hearn Ave from Stony Point Rd to Dutton Ave, Range Ave from Jennings to Guerneville Rd, Range Ave from Russell Ave to Bicentennial Way. Completion of this project is vital to the integrity of our community infrastructure. Project Details
(Zack Albers - Ghilotti Construction / City - Danny Chen)

Railroad Depot Restrooms Accessibility Alterations
To provide accessibility upgrades to the existing Railroad Depot restrooms. 
Project Details
(Joe Pycz,- Kirby Constructions Company, Inc - 707- 526-0880 / City - Felicia Ong)

Slater Street and Lewrosa Way Sewer and Water Main Replacement Project
This project will replace aged water main and sewer main in Lewrosa Way and in Slater Street from Lewis Road to Dexter Street. The pavement will be reconstructed along Slater Street between Lewis Road and Dexter Street and in Lewrosa Way and nine existing curb ramps will also be replaced. 
Project Details
(Argonaut Constructors - Trevor Stewart / City - Sara Mathews)

Six Fire Damaged Parks Recovery
This project will repair damages caused by 2017 Tubbs Fire at six locations including Fir Ridge Park, Nagasawa Community Park, Rincon Ridge Open Space and Park, Francis Nielsen Park, and Parkerhill Trail. A new playground equipment will be installed at Fir Ridge Park. Project Details
(Oak Grove Construction – Mark Neumann (707) 292-6710, Consultant Inspection–Ryan Curry / City – Danny Chen)

Terra Linda and Buena Vista Sewer and Water Replacement – Phase I
This project will upgrade existing 6-inch water mains along Terra Linda Dr. to remediate fire flow deficiencies. Aged sewer mains (1961) will be replaced congruently to minimize the potential for future deficiencies. Water and Sewer mains in Terra Linda Ct. will also be replaced. The pavement will be reconstructed along Terra Linda Dr. to Buena Vista and in Terra Linda Ct. once mains have been replaced. ** Note: This project is separate from PID00158 North Trunk Sewer Replacement -Mendocino Ave to Terra Linda Dr. Project Details
(Team Ghilotti – Joe Moreira (707) 953-9613 / City – Sara Mathews)

Water Tanks Tree Removal
This project will evaluate trees at five Water facilities to determine whether they pose a hazard to the tank, other infrastructure, or public safety. Identified hazard trees will be removed.
(Atlas Tree - Corin Burns - Project Manager (707)280-5788 / City - Sara Mathews)

Private Development Projects – Engineering Development Services

888 4th Street – 891 3rd St.
City File #2022-0023 – (EP20-1160)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023
(EG Paving – Fego Garcia – 707-843-9558/City – Susan Mays)

Acacia East Subdivision – 660/664 Acacia Ln.
City File #2018-0011 – (EP21-0945)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023
(RCX Inc – Casey Helmick – 707-591-5671/City – Susan Mays)

Airway Community Care – 3731 Airway Drive
City File #2018-0008 – (EP19-0687)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023
(Serres Construction - John Serres 707-799-5557/City – Nick Calabrese)

Bellevue Ranch (Ph#7) – 2903 Dutton Meadow Ave.
City File #2020-0042 – (EP22-0489)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through July 2023
(Northwest General Engineering - Adam Holtzinger – 707-975-6769 /City - Javier Fernandez)

Colgan Village Phase 1 & 2 – 3011 Dutton Meadows Ave.

City File # 2018-0012 - (EP22-0142) – 2020-0040 – (EP22-0181)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(Argonaut Constructors –  John Santos – 707- 235-0218 /City - Javier Fernandez)

Caritas Village Phase 1 & 2 – 465 A Street x 6th/7th Streets
City File #2021-0014 - (EP21-0525/EP21-1214)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(RCX Inc – Casey Helmick – 707-591-5671/City - Javier Fernandez)
(Ghilotti Brothers – Brendan Smith - 415-290-3355)

Dutton Ave (Old Dominion Freight Line) – 2960 Dutton Ave.
City File #2021-0034 – (EP22-0570)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(Northwest General – Ben Guillory – 707-888-9120/City – Nick Calabrese

Grove Village – 2872 Stony Point Rd 
City File #2020-0020 – (EP21-0524)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023.
(Andy Thomas (City Ventures) 925-324-0132/City – Javier Fernandez)

Holly Hock Subdivision – 1650 Meda Ave (Brookwood Ave)
City File # #2019-0011
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023.
Street, sidewalk and utility improvements.
(Argonaut Constructors – Trevor Stewart – 707-332-2447 /City - Javier Fernandez)

Juniper Ave – 3192 Juniper @ Bellevue Ave 
City File #2021-0038 – (EP21-1387)
Street and utility improvements.
(Sunshine Construction – Danny Dortch– 707-974-4569 /City - Javier Fernandez)

Kawana Meadows Subdivision – Franz Kafka Ave at Kawana Terrace
File #2005-0040 – (EP15-0548)

Street, sidewalk and utility improvements.
(Propris Properties - Louis Rousseau-Mata - 831-400-9473 /City - Javier Fernandez)

Kawana Springs Apartments – 500 Kawana Springs Rd.
City File #2021-0030 – (EP21-0075)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(Ghilotti Bros. – Brendan Smith – 415-290-3355/City – Javier Fernandez/Susan Mays)

Kerry Ranch Subdivision – 2181 Francisco Ave x San Miguel Ave.
City File #2019-0037 – (EP21-0643) 
Street, sidewalk and utility improvements.
(Argonaut Constructors – Dan Giordani – 707-280-4986 /City – Nick Calabrese)

Liner Village Subdivision – 2063 Dennis Ln / 3804 Elwin Ln
City File #2018-0024 – ENGG20-004 – (EP21-0063)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023.
Street, sidewalk and utility improvements.
(Jason Jones Construction – Jason Jones – 707-543-6529 /City – Nick Calabrese)

Lotus Court (Store More) – 1235 Lotus Ct (Barham Ave/Santa Rosa Ave)
City File #2022-0035 – (EP22-1156) 
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(RCX – Casey Helmick – 707-591-5671 /City – Susan Mays)

Mahonia Glen – 5173 Hwy 12 (Calistoga Rd.)
City File #2022-0032 – (EP22-1192)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023
Street, sidewalk and utility improvements.
(Serres Construction - John Serres 707-799-5557/City – Javier Fernandez/Susan Mays)

Marlow Commons Subdivision – 2039 Guerneville Rd.
City File #2019-0037 – (EP19-1291)
Street, sidewalk and utility improvements.
(Argonaut Constructors – Dan Giordani – 707-280-4986 /City – Nick Calabrese)

Mendocino Ave. (Journey’s End) – 3575 Mendocino Ave
City File #2021-0028 – (EP21-1227)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023.
Street, sidewalk and utility improvements.
(Ghilotti Construction – Tony Mencarini – 707-978-0537 /City - Javier Fernandez)

Old Stony Point Rd Apartments – 2542 Old Stony Point Rd/ Hearn Ave
City File #2022-0002 – (EP22-0111)
Street, sidewalk and utility improvements. 
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through May 2023.
(Serres Construction - John Serres 707-799-5557/City – Nick Calabrese)

Petaluma Hill Rd. (38 Degrees North Phase 2)
City File #2022-0015 – (EP22-0360)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023.
(Northwest General Engineering - Adam Holtzinger – 707-975-6769 /City - Javier Fernandez)

Piner Rd (Self Storage) – 970 Piner Rd.
City File #2023-0006 – (EP22-0160)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023.
(Peters Excavating – Ron Peters – 707-953-6136/City – Javier Fernandez)

Pullman Lofts – 701 Wilson
City File #2021-0005 – (EP21-0424)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through June 2023
(Northwest General Engineering - Adam Holtzinger – 707-975-6769 /City – Javier Fernandez)

Round Barn Village – 1 Round Barn Blvd.
City File #2020-0004 – (EP20-0175)
On-site grading and private improvements. Off-site utility connections.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
(Serres Construction - John Serres 707-799-5557/City – Javier Fernandez)

Santa Rosa Ave (In & Out Burger) – 2532 Santa Rosa Ave
City File #2022-0012 – (EP22-0461)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through June 2023
(Northwest General Engineering – Ben Guillory – 707-888-9120 /City – Susan Mays)

Schellinger-Burbank Subdivision – 1400 (1609,1720,1780) Burbank Ave.
City File #2022-0034 – (EP22-0461)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023.
(Northwest General Engineering - Jason Holtzinger – 707-481-9135 /City - Javier Fernandez)

Sebastopol Rd (1885) Acme Apartments
City File #2022-0030 – (EP22-0696)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2023
Street, sidewalk and utility improvements.
(RCX – Casey Helmick – 707-591-5671 /City – Nick Calabrese)

South Park Commons – 704 Bennett Valley Rd. (Rutledge Ave)
City File - none – (EP22-1115)                                                                                                                                     
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
Street, sidewalk and utility improvements.
(Ghilotti Construction – Tony Mencarini – 707-978-0537 /City - Javier Fernandez)
 

Stony Point Flats – 2268 Stony Point Rd.
City File #2022-0036 – (EP23-0130)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023.
(Peters Excavating – Ron Peters – 707-953-6136/City – Javier Fernandez)

Stony Village North – 2729 Stony Point Rd. 
City File #2020-0001 – (EP20-0186)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through June 2023.
(Northwest General Engineering – Mark Casarotti – 707-974-4568 /City - Javier Fernandez)

West College Apartments – 2150 West College Ave.
City File #2021-0042 – (EP22-0427)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through July 2023
Street, sidewalk and utility improvements.
(RCX Inc – Casey Helmick – 707-591-5671/City – Nick Calabrese)

West College Aviara Apartments – 1385 West College Ave.
City File #2022-0031 – (EP22-0969)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through July 2023
Street, sidewalk and utility improvements.
(Northwest General Engineering – Ben Guillory – 707-888-9120/City – Nick Calabrese)

West 3rd Street (Cannery) – 3 West 3rd. St.
City File #2023-0011 – (EP23-0248)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through July 2023
Street, sidewalk and utility improvements.
(Benchmark Construction – Joel Gentry – 707-254-8705/City Javier Fernandez)
 

 

 

 

 

 

 

 

 

 

All dates and times are subject to change.
Work will be done Monday through Friday unless otherwise noted.
Access for emergency vehicles will be provided.
 Postal delivery will continue as usual.