Construction Bulletin

City Projects - Capital Projects Engineering

Albany, Clement and Malano Sewer and Water Improvements
This project will upsize water mains in Albany St, Malano Ct, Clement Ave, and Emeritus Circle to increase fire flows and reduce maintenance costs. The project will replace existing VCP sewer mains in Albany Dr from Oliver to Elliot, Clement Ave from Albany to Malano Ct and in Malano Ct., eliminating three sewer mains and storm crossings and a backyard sewer easement. These sewer improvements will reduce maintenance costs and inflow and infiltration. The pavement in the project area will be reconstructed.
(TerraCon Constructors, Inc. - Brian Lydon / City - Richela Maeda) Project Details

Backup Generators at Water and Wastewater Facilities
This project will replace existing emergency generators and related equipment at 18 water and wastewater facilities in and around Santa Rosa. These upgrades increase generator capacities, update aging equipment, transition facilities to more reliable fuel sources, and decrease greenhouse emissions. This project will also update transfer switches, electronics, concrete pads, and structures as necessary to accommodate the new equipment.  Project Details  
(Terracon Constructors – Brian Lydon / City – Charles Robinson)

Cleveland Ave & St. Rose District Sewer & Water Improvements
This project will abandon approximately 700 feet of clay sewer main on the west side of Cleveland between Ridgway Avenue and Carrillo Street by transferring 23 laterals to an existing PVC sewer trunk on the east side of Cleveland Avenue. Additionally, this project will include sewer system improvements for 7th Street and B Street. The work on 7th Street will abandon 540 feet of clay sewer main and transfer 2 laterals to an existing sewer trunk between A Street and B Street. The work on B Street includes replacing a 30-foot section of deteriorated pipe near Healdsburg Avenue. This work will reduce inflow and infiltration and reduce maintenance costs. Project Details
(W.R. Forde Associates - Tony Perez / City - Sara Mathews)

Cobblestone Dr Zone R2-R4 Water Main Connection
The project will install approximately 1,045 linear feet of new 10-inch diameter water main and a pressure-reducing assembly that will connect a high-pressure zone with a lower-pressure zone to improve fire protection in the Cobblestone neighborhood. Approximately 174 linear feet of 8-inch diameter water main will be added near the southern end of Cobblestone Drive to provide operational flexibility including the ability to isolate the Cobblestone neighborhood into a separate pressure zone.  Project Details
(Team Ghilotti, Inc - Joe Moreira / City - Andrew Wilt)

Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery
This project will rehabilitate approximately 33 miles of City residential streets that were damaged as result of debris removal activities in Coffey Park and Fountaingrove neighborhoods following the 2017 Tubbs Fire. Two treatment options are proposed for streets included on this project, 1) mill and fill asphalt replacement and 2) digout repairs with a slurry seal. Treatment type for any given street is dependent on roadway condition. Please see below links for proposed pavement treatment maps in the Coffey Park and Fountaingrove neighborhoods. Project Details
(Argonaut Constructors, Inc - John Carlisle / City- Felicia Ong)

Cooper Drive Emergency Repair
This project will temporarily reinstate approximately 100 lineal feet of the drainage flow from a broken concrete v-ditch within an easement, and install a new French drain to capture underground water. The main intent of this project is strictly a temporary measure in hope to avoid land erosion due to ground saturation while the City seeks out a more permanent repair solution through design process. Project Details
(Nelson Construction- Robert Heaton/ City- Roger Wu)

E Haven Dr Sewer and Water Improvements - Eleanor Ave to E Foothill Dr
This project is part of the replacement of the Grace neighborhood water and sewer mains. This project will replace undersized and aged water main and aged and obsolete sewer main in East Haven from Eleanor Avenue to East Foothill Drive, in Hawthorne Court, Iris Court and Eleanor Avenue. This project will also replace aged and obsolete sewer main in East Foothill Drive between Thomas Drive and Siesta Lane. Upsizing the water mains will improve fire flow and reduce maintenance costs. Replacing older deteriorated VCP pipe reduces inflow and infiltration and reduces maintenance costs. Pavement will be reconstructed. Project Details
( Argonaut Constructors -Dan Giordani (707) 542-4862 / City - Sara Mathews)

Emergency Well Pump Station – A Place to Play 
The purpose of this project is to convert the existing test well to an Emergency Groundwater Well, along with design and construction of a well pump station and appurtenances associated with the Emergency Groundwater Well at A Place to Play Park. This work is being implemented under the Groundwater Master Plan, for more information, go to the Santa Rosa Water’s Groundwater website located at: https://srcity.org/857/Groundwater. Project Details
(Team Ghilotti - Joe Moreira / City - Chris Huffman)

Finley Aquatic Center Spray Ground and Renovation Project 2023
This project will propose major upgrades to the Finley Aquatic Center infrastructure including the demolition of the existing wading pool. New construction is to include developing a new spray ground in place of the existing kiddie pool. The kiddie pool and raised lawn area behind the kiddie pool will be replaced with a new interactive splash pad equipped with a variety of automatic and manually operated spray features, an expanded picnic area, and additional renovation improvements to the facility that will ensure compliance with the Americans with Disabilities Act (ADA). Project Details
(Waterworks Industries, Inc – Mathais Toupin (707) 837-7900/ Kleinfelder Consultant - Thomas Fakner (408) 595-3275)/ City – Delta Beaston)

Fire Damaged Roadway Landscaping
This project relates to the repair of the irrigation systems along the city owned and maintained roadway landscaping areas such as in planter strips and medians as the result from 2017 Tubbs Fire. The project limits are spread out across Fountaingrove and Coffey Park neighborhoods. The scope of the work includes the removal of the existing fire damaged irrigation systems, removal of approximately 300 trees in conflict with the proposed improvements, install new irrigation systems per city code. Project Details
(Bortolussi & Watkin, Inc-Juan Maravilla (415)453-4675 / Green Valley Consultants- Jason Balatti (707) 579-0388 / City - Danny Chen)

Fire Station 5 Resiliency and Relocation
This project will rebuild Fire Station No. 5, lost to the 2017 Tubbs Fire, at a new location on the southeast corner of Stagecoach Road and Fountaingrove Parkway. The new location will improve response times to the service area, and allow for a larger facility able to support upstaffing during significant weather events and to be utilized as a forward command post in an emergency. The new one-story 8,960 square foot Essential Services fire station includes emergency resiliency materials and technology, and environmentally friendly features. Project Details
(Wright Contracting LLC -Steve McCulloch / City- Camron MacDonald)

Fulton Road From Guerneville Road to Piner Road – Widen to Four Lanes
The Project will widen and reconstruct Fulton Road into four vehicle travel lanes with a median using roller compacted concrete (RCC), between Guerneville and Piner Road. The project widening will improve the City’s transportation network and promote multi-modal transportation with the installation of bike lanes and sidewalk widening along this one-mile corridor. This project has been envisioned in the Santa Rosa 2035 General Plan as an arterial/regional road to be widened to improve circulation, safety, and operation along Fulton Road. The Project is expected to begin construction in June 2022 and will take eighteen months to complete. Residents should expect traffic delays and watch for changing traffic conditions during construction. Project Details
(Ghilotti Bros / Vanguard Construction JV  - Casey Wood / Green Valley Consultants - Tom Gorman / City - Chad Anderson)

Geysers - Delta Connection Improvements
This project will upsize approximately 130 linear feet of the existing 12" diameter connection between the Geysers Pipeline and Delta Pond to 24" diameter. This will allow high flows of recycled water to be delivered to Delta Pond using the Geysers pipeline as a redundant supply line to the reclamation piping network. Project Details
(Piazza Construction - James Piazza / Consultant – Brelje and Race - Dana Brock / City – Michael Mirich)

Laguna Treatment Plant Disinfection Improvements Project
Ultraviolet light (UV) is the primary disinfection process for the City of Santa Rosa's Laguna Treatment Plant (LTP). The existing system was commissioned in 1998, has reached the end of its useful life, and no longer has the treatment capacity for peak wet weather sewer flows. Project Details
(Shimmick Construction - Jason Burden / Psomas - Chris Davenport)

Laguna Treatment Plant Emergency Generator Fuel Tank and Fleet Fueling Station Replacement
The outer wall of the existing emergency generator diesel fuel storage tank at the Laguna Treatment Plant has started to deform preventing monitoring of the annual space thus is out of compliance from a regulatory standpoint. The fuel storage tank is critical to insuring operation of the plant in the event of a power outage. The new tank will be an above ground storage tank. The project will replace the plant's existing diesel fueling station with a dual diesel/gasoline fueling station. Project Details
(CIC - Tuan Pham / City - Liz Hanley)

Laguna Treatment Plant Waste Gas Burner Replacement
This project will replace the Laguna Treatment Plant’s existing waste gas burner, which combusts any excess digester gas from the plant’s cogeneration system. The waste gas burner is nearing the end of its useful life and requires replacement to provide the plant with a safe and compliant system. 
Project Details
(Pacific Intrastructure - Mark Jorgenson / City - Liz Hanley)

Los Alamos Trunk Sewer Replacement Segment 1 (Streamside Dr to Elaine Dr)
This project will replace approximately 5300 linear feet of the existing Los Alamos Trunk sewer that was installed in the 1950s that is undersized and in poor condition. The new trunk sewer will be 24-inches in diameter and will generally be installed adjacent to the existing alignment between Streamside Dr and Elaine Dr through private property and along Mission Circle and Quigg Dr. An above-ground sewer bypass system will be installed for short durations at certain locations before being relocated as it follows the construction progress along the alignment. To minimize both public and business impacts, a portion of the work along Mission Circle is conditioned night work and the proposed water improvements serving 4920 and 4934 HWY 12 are conditioned weekend work. Los Alamos Sewer Project
Project Details
(Team Ghilotti - Joe Moreira / City - Andrew Wilt)

Santa Rosa Avenue Corridor Improvements
This project will make improvements to existing pedestrian, bike, transit, and vehicle facilities along Santa Rosa Avenue between Sonoma Avenue and Maple Avenue. The project will upgrade pedestrian facilities throughout the corridor, including upgrading pedestrian ramps to current ADA standards, and close gaps in the Class II bike lane network on Santa Rosa Avenue, while considering connectivity to Sonoma Avenue. Project Details
(Granite Construction – Erik Owenson / City – Delta Beaston)

Sonoma Ave. Pavement Rehabilitation – E St. to Bobelaine Dr.
The project includes rehabilitating approximately 0.9 center line miles of this roadway due to failing and deteriorating pavement conditions by milling and replacing 0.25' of hot mixed asphalt on all through lanes including the second through and merge lanes at the intersections of Brookwood Ave and E St., followed by pavement grid for additional strength and pavement life, followed by a 0.25' hot mixed asphalt overlay. Existing Class II bike lanes will be maintained and pedestrian ramps will be reconstructed to current ADA standards. Approximately 75 Water services within the project limits will also be replaced. Project Details
(Ghilotti Bros. – Casey Wood / City – Charles Robinson)

Water Tanks Tree Removal
This project will evaluate trees at five Water facilities to determine whether they pose a hazard to the tank, other infrastructure, or public safety. Identified hazard trees will be removed.
(Atlas Tree - Corin Burns - Project Manager (707)280-5788 / City - Sara Mathews)

Private Development Projects – Engineering Development Services

888 4th Street – 891 3rd St.
City File #2022-0023 – (EP20-1160)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023
(EG Paving – Fego Garcia – 707-843-9558/City – Susan Mays)

Acacia East Subdivision – 660/664 Acacia Ln.
City File #2018-0011 – (EP21-0945)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
(RCX Inc – Casey Helmick – 707-591-5671/City – Susan Mays)

Airway Community Care – 3731 Airway Drive
City File #2018-0008 – (EP19-0687)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023
(Serres Construction - John Serres 707-799-5557/City – Nick Calabrese)

Arbors Townhomes – 3500 Lake Park Drive
City File #2020-0022 – (EP22-0428)

Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through September 2024
(Argonaut Contractors – Trevor Steward 707-332-2447/ City – Javier Fernandez)

Bellevue Ranch (Ph#7) – 2903 Dutton Meadow Ave.
City File #2020-0042 – (EP22-0489)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through November 2023
(Northwest General Engineering - Adam Holtzinger – 707-975-6769 /City - Nick Calabrese)

Colgan Village Phase 1 & 2 – 3011 Dutton Meadows Ave.

City File # 2018-0012 - (EP22-0142) – 2020-0040 – (EP22-0181)
Street, sidewalk and utility improvements.
(Argonaut Constructors –  John Santos – 707- 235-0218 /City - Nick Calabrese)

Fountaingrove Inn – 3586 Mendocino Ave.
City File #2023-0017 – (EP23-0156)

Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
(Northwest General Engineering – Doug Noren 707-615-2753/City – Javier Fernandez)

Grove Village – 2872 Stony Point Rd 
City File #2020-0020 – (EP21-0524)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023.
(Andy Thomas (City Ventures) 925-324-0132/City – Nick Calabrese)

Holly Hock Subdivision – 1650 Meda Ave (Brookwood Ave)
City File # #2019-0011
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023.
Street, sidewalk and utility improvements.
(Argonaut Constructors – Trevor Stewart – 707-332-2447 /City - Susan Mays)

Juniper Ave – 3192 Juniper @ Bellevue Ave 
City File #2021-0038 – (EP21-1387)
Street and utility improvements.
(Sunshine Construction – Danny Dortch– 707-974-4569 /City - Javier Fernandez)

Kawana Meadows Subdivision – Franz Kafka Ave at Kawana Terrace
File #2005-0040 – (EP15-0548)

Street, sidewalk and utility improvements.
(Propris Properties - Jon Chan 408-883-3884, Ext. 702 /City - Javier Fernandez)

Kawana Springs Apartments – 500 Kawana Springs Rd.
City File #2021-0030 – (EP21-0075)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
Street, sidewalk and utility improvements.
(Ghilotti Bros. – Brendan Smith – 415-290-3355/City – Susan Mays)

Kerry Ranch Subdivision – 2181 Francisco Ave x San Miguel Ave.
City File #2019-0037 – (EP21-0643) 
Street, sidewalk and utility improvements.
(Argonaut Constructors – Dan Giordani – 707-280-4986 /City – Nick Calabrese)

Liner Village Subdivision – 2063 Dennis Ln / 3804 Elwin Ln
City File #2018-0024 – ENGG20-004 – (EP21-0063)
Street, sidewalk and utility improvements.
(Jason Jones Construction – Jason Jones – 707-543-6529 /City – Nick Calabrese)

Lotus Court (Store More) – 1235 Lotus Ct (Barham Ave/Santa Rosa Ave)
City File #2022-0035 – (EP22-1156) 
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
Street, sidewalk and utility improvements.
(RCX – Casey Helmick – 707-591-5671 /City – Susan Mays)

Mahonia Glen – 5173 Hwy 12 (Calistoga Rd.)
City File #2022-0032 – (EP22-1192)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
Street, sidewalk and utility improvements.
(Serres Construction - John Serres 707-799-5557/City – Susan Mays)

Mendocino Ave. (Journey’s End) – 3575 Mendocino Ave
City File #2021-0028 – (EP21-1227)
Street, sidewalk and utility improvements.
(Ghilotti Construction – Tony Mencarini – 707-978-0537 /City - Javier Fernandez)

Petaluma Hill Rd. (38 Degrees North Phase 2)
City File #2022-0015 – (EP22-0360)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through March 2024.
(Northwest General Engineering - Adam Holtzinger – 707-975-6769 /City - Javier Fernandez)

Piner Rd (Self Storage) – 970 Piner Rd.
City File #2023-0006 – (EP22-0160)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through October 2023.
(Peters Excavating – Ron Peters – 707-953-6136/City – Javier Fernandez)

Round Barn Village – 1 Round Barn Blvd.
City File #2020-0004 – (EP20-0175)
On-site grading and private improvements. Off-site utility connections.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
(Serres Construction - John Serres 707-799-5557/City – Javier Fernandez)

Schellinger-Burbank Subdivision – 1400 (1609,1720,1780) Burbank Ave.
City File #2022-0034 – (EP22-0461)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023.
(Northwest General Engineering - Jason Holtzinger – 707-481-9135 /City - Javier Fernandez)

Sebastopol Rd (1885) Acme Apartments
City File #2022-0030 – (EP22-0696)
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
Street, sidewalk and utility improvements.
(RCX – Casey Helmick – 707-591-5671 /City – Nick Calabrese)

South Park Commons – 704 Bennett Valley Rd. (Rutledge Ave)
City File - none – (EP22-1115)                                                                                                                                     
Street, sidewalk and utility improvements.
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023
(Ghilotti Construction – Tony Mencarini – 707-978-0537 /City - Javier Fernandez)
 

Stony Point Flats – 2268 Stony Point Rd.
City File #2022-0036 – (EP23-0130)
Street, sidewalk and utility improvements.
Intermittent traffic control 8:30 a.m. - 4:30 p.m., Monday to Friday, through December 2023.
(Peters Excavating – Ron Peters – 707-953-6136/City – Javier Fernandez)

West College Aviara Apartments – 1385 West College Ave.
City File #2022-0031 – (EP22-0969)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through November 2023
Street, sidewalk and utility improvements.
(Northwest General Engineering – Ben Guillory – 707-888-9120/City – Nick Calabrese)

West 3rd Street (Cannery) – 3 West 3rd. St.
City File #2023-0011 – (EP23-0248)
Intermittent traffic control 7:30 a.m. - 4:30 p.m., Monday to Friday, through March 2024
Street, sidewalk and utility improvements.
(Benchmark Construction – Joel Gentry – 707-254-8705/City Javier Fernandez)
 

 

 

 

 

 

 

 

 

 

All dates and times are subject to change.
Work will be done Monday through Friday unless otherwise noted.
Access for emergency vehicles will be provided.
 Postal delivery will continue as usual.