Pacific Avenue Pavement Reconstruction

SB1-Logo - reduced size
Pacific Avenue Reconstruction Map

Update: 9.16.21

Underground utility work will be ongoing between King Street and Humboldt Street and at other locations outside of the right of way for the next month. Following completion of underground utility work, the contractor will transition back to paving activities, starting with base paving on Pacific Avenue between King Street and Humboldt Street. Once base paving is complete, the contractor will finalize all surface paving for the entire project, which is scheduled to be completed not later than November 19th, or the week prior to Thanksgiving. Traffic delays are to be expected in the area, please avoid the construction area if possible.

________

Update: 9/2/21

Substantial completion of the paving operations from Montecito to King Street happened at the end of last week. The pavement in this area will remain lower than the adjacent roadway until the final pavement section can be placed over the entire project area.

The underground work between King Street and Humboldt Street was delayed due to material availability until this week, which has pushed out the paving operations in that area. Work has started on the underground and it is expected to continue through September. Traffic delays are be expected in the area, please avoid the construction area if possible.

________

Update: 8/9/21

Paving operations within the project area is anticipated to begin August 16, 2021 and will require approximately 8 weeks to complete. During the paving process, Pacific Avenue will remain open to thru traffic, however delays are to be expected, so motorists are advised to take alternate routes when possible. There will also be times when parking will be restricted within the project limit to allow construction crews full access to the roadway as well as to allow traffic to move through the work zone. No parking notices will be placed on the street 72 hours prior to the start of work and will remain until the work is complete.

This project will reconstruct Pacific Avenue between Humboldt Street and Montecito Avenue:

  • Reconstruct/update 37 curb ramps at intersections along Pacific Avenue between Humboldt Street and Montecito Avenue to meet State and Federal ADA accessibility standards.
  • Replace approximately 300 feet of sewer main.
  •  Replace water main, (45) water services and (6) hydrants    
  • Replace 0.7-miles of water main 
  • Replace 280 feet of storm drains and (9) catch basins  
  • Install pedestrian and traffic signal improvements      
  • Install Rectangular Rapid Flashing Beacon (RRFB) systems, pedestrian activated crosswalk warning devices at the intersections of King Street, Beaver Street and Elizabeth Way/Spring Street.  
  • Install three traffic signal video detection systems to improve traffic signal responses for vehicle and bicycle users at Humboldt Street, North Street and McDonald Avenue intersections.  


Project Schedule

Complete Design June 2020
Begin Construction November 2020
Complete Construction December 2021
For more information please contact:
​          Lisa Welsh
​          Associate Civil Engineer
​          City of Santa Rosa
​          lwelsh@srcity.org
​          707-543-3909

​