PG&E’s relocation of its transformer is now scheduled and work to re-wire electrical service to the Galvin tennis court lights will follow. Electrical service to structures nearby the tennis courts such as the restroom building will be shut off on August 24, 2017 so that PG&E can reconnect full service to the tennis courts by the end of the day on August 25, 2017. Signage will direct citizens to other nearby restrooms available while the power is out temporarily. Barring any unforeseen issues, power to the tennis courts and the restroom building will be operational by the end of the day on August 25, 2017. The electrical contractor will continue with a few minor construction items on August 28, 2017 and electrical service will remain operational during their work.