Recovery Update for Six Fire-Damaged Parks in the Fountaingrove Area

NF_Recovery Project Update

Debris removal and restoration for all six fire-damaged parks and open space parcels in the Fountaingrove area began in May and due to the tight schedule, work is occurring concurrently at all six locations. To date, all fire-damaged materials have been removed and rebuilding is well underway. The affected parks and open space areas include Rincon Ridge Neighborhood Park, Rincon Ridge Open Space, Fir Ridge Neighborhood Park, Nagasawa Community Park, Francis Nielsen Neighborhood Park, and Parker Hill Trail.

Restoration at Fir Ridge Park includes the completed replacement of the basketball court and concrete steps with installation of the new irrigation system expected to be completed in the next few weeks. Two play structures damaged in the wildfire are scheduled to begin installation next month. The new play structure designs were selected based on community input. View play structure designs here

Replacement irrigation water lines have been installed and tested at Rincon Ridge Park. New benches, drinking fountains and trash, recycle and compost receptacles are planned for installation over the next two weeks. New trail fencing within Rincon Ridge Open Space is currently under construction.

Park benches, and trash, recycle and compost receptacles are being installed at Francis Nielsen Park, and a new wood trail fence is currently underway along Parker Hill Trail. The two pedestrian bridges destroyed in the wildfire along Parker Hill Trail and the one pedestrian bridge in Frances Nielsen Park were replaced in 2019.

The picnic surface area at Nagasawa Park has been replaced with amenities including installation of benches around the park coming soon.

Construction costs to restore the six parks and open space parcels is estimated at $1.5 million. The funding was obtained through FEMA, Cal OES, and PG&E settlement funds. The recovery project is expected to be completed in November 2022.

Facebook Twitter Email

Other News in Transportation & Public Works - News

NF_Ride Fare Free Today v2

Ride CityBus Fare-Free Today

Posted on: September 6, 2022
NF_Zero Waste Week

2022 North Bay Zero Waste Week

Posted on: June 30, 2022
NF_Skyhawk OS Open

Skyhawk Open Space Open to the Public

Posted on: February 26, 2021
NF_Vaccine Ride

When Vaccination is Your Destination

Posted on: February 16, 2021
Sewer Replacement Projects

Sewer Replacement Projects

Posted on: January 28, 2021
NF_Colgan Creek Park Survey

Colgan Creek Park Survey

Posted on: December 23, 2020
SR Transit Resumes Fare Collections

Transit Fare Collections to Resume 2.1.21

Posted on: December 21, 2020
Rain Ready - Sand bag pile

City Sandbag Filling Station Open

Posted on: December 15, 2020
CityBus Joins the Clipper START Program

CityBus Joins Clipper START Program

Posted on: November 19, 2020
News Flash CityBus

Celebrate Safety with CityBus

Posted on: October 15, 2020