Posted on: February 23, 2018

[ARCHIVED] Stony Point Road Widening and Reconstruction Project

Stony Point Road Project

Stony Point Road Reconstruction & Widening Project  

The City of Santa Rosa would like to thank you for your patience throughout this time of construction. We are working closely with our contractors to minimize impacts and keep residents informed. For your convenience, weekly updates will be posted on this project website, and we invite you to stay connected with us on social media to help you navigate through affected areas.

Update: April 13, 2018

Final Surface Paving Scheduled Next Week

Depending on weather conditions, final paving activities are scheduled next week and may extend into the weekend and the following week. Construction crews will complete paving preparations and install the final surface from south of Hearn Avenue to Sebastopol Road. Expect daily lane shifts on Stony Point Road, one lane will remain open in each direction during construction. Flaggers will hold cross street traffic at intersections while the pavement is placed and compacted within the intersection, so allow extra time to travel through the area. 


Please drive carefully, follow traffic control signage and construction flaggers. Construction hours are 7 AM to 5PM, however conditions may require work to extend later.


Other activities will include continuation of concrete work, road striping and landscaping. 


Expect delays and use alternate routes (Highway 12 and Highway 101 are strongly advised). Be prepared for possible delays at bus stops due to the paving work.

 

 We appreciate your patience and cooperation during construction.


What We Are Doing

Now, through Summer of 2018, the final construction phase of the Stony Point Road widening and reconstruction project is underway. In this final phase, Stony Point Road will be widened into four lanes from Sebastopol Road to Hearn Avenue and then taper into two lanes with a middle turn lane from Hearn Avenue to Barndance Lane. We are widening Stony Point Road to help alleviate traffic congestion; enhance safety; facilitate the flow of vehicular, pedestrian and bicycle traffic; and improve connectivity between the north and south sections of Santa Rosa.

Key Improvements

  • Additional travel lanes will be added to Stony Point Road
  • The roadway will be completely reconstructed and repaved
  • Bicycle lanes will be added on both sides of Stony Point Road
  • The Roseland Creek culvert bridge will be widened
  • Construction of permanent features, such as retaining walls and sound walls
  • New sidewalk and curb ramps will be constructed
  • Traffic signal improvements at six intersections
  • A landscaped median will be added
  • Street lighting will be enhanced along this corridor

Additional Info...
Facebook Twitter Email

Other News in Transportation & Public Works - News

NF_Stuff the Bus 300x190

Stuff the Bus Toy Drive

Posted on: November 27, 2023
NF_Joe Rodota Trail Closed

Joe Rodota Trail Temporary Closure

Posted on: November 15, 2023
CityBus Electric Bus Ribbon Cutting

City to Launch Four New Electric Buses

Posted on: December 22, 2022
Zero Waste Holiday Resolutions

Zero Waste Holidays: New Year Resolutions

Posted on: December 13, 2022
Zero Waste Holiday Entertaining

Zero Waste Holiday Entertaining Tips

Posted on: November 27, 2023
NF_Break Out the Rake

Break Out the Rake!

Posted on: October 26, 2022
NF_Leaf Season 1

Where You Leave Your Leaves Matters!

Posted on: October 20, 2022
NF_Ride Fare Free Today v2

Ride CityBus Fare-Free Today

Posted on: September 6, 2022
NF_Zero Waste Week

2022 North Bay Zero Waste Week

Posted on: June 30, 2022